Vinyl floor construction

Vinyl floor construction

Vinyl floor construction methods: 

1, plain deal: According to prime position to do sanding, repair, removal; 

2, vinyl ester primer: The appropriate proportion of vinylester resin and a curing agent added to promote the prime land thin scratch againenhance the surface adhesion;

 3, Shop glass fabric: place the flat glass fabric, vinylesters with deployment of a good paint adhesion to glass woven ground, and use batchcutter vinyl ester coating batch will be flat, uniformly coating, according to need to do oneto three;

 4, vinyl ester coating: vinyl esters deployment of good paint with a trowel uniform coating one to two; 

5, vinyl ester finish: finish the deployment of good vinyl ester uniform coating with a trowel, after the completion of the overall bright and clean surface, coloruniform, no hollowing; 

6, the construction complete: 24 hours before the Master, 72 hoursbefore stress. (25 degrees prevail, low temperature be modest extension of opening hours) 

7, maintenance